Thursday, August 13, 2026

Update: New Turner Hall Making Progress

 

What a difference a year makes! 

As SC State students returned to campus on August 10 to begin the new school year, it is clear that the new Turner Hall academic building has made great progress since May. 








This photo is from one year ago, August 2025. The construction was just getting underway. 












In an update this week, the university says crews have completed the steel structure or framework and are now pouring concrete for each floor. 








The $54.7 million 94,000-square-foot building is scheduled to open next year, hopefully in time for the start of the 2027-2028 school year.